Prepare a master production schedule for industrial pumps in the manner of the following table. Use the MPS rule to “schedule production when the projected on-hand inventory would be less than 10 without production.” Suppose that a production lot size of 70 pumps is used. (Leave no cells blank – be certain to enter “0” wherever required.)JuneJuly6412345678Forecast3030303040404040Customer orders (committed)33201042Projected on-hand inventory[removed][removed][removed][removed][removed][removed][removed][removed]MPS[removed][removed][removed][removed][removed][removed][removed][removed]ATP[removed][removed][removed][removed][removed][removed][removed][removed]